Pioneering industrial campus

Projects
Renovation of existing buildings
Agricultural projects
Building 1712
- Reception, offices, conference rooms, co-working facilities
- Offices, shared laboratories for start-ups (Agri & Co Challenge competition)
- Investment: 300,000
-
-
Building 1715
- Redeployment of the kennel as an experimental greenhouse for trials
- Capital expenditure: 800,000
-
-
Building 1701
- Reception, offices, conference rooms, co-working facilities
- Investment: $4 million
-
-
Building 1710
- Laboratories, offices, small production, laboratories and offices for SQTS
- Completion: 2022/2023
- Estimated investment (1710 + 1720): $17.8 million
Building 1720
- Restaurant for the site
- 2022: planning
- 2022/2023: completion
- Estimated investment (1710 + 1720): $17.8 million
-
-
Building 1740
- Reconstruction of existing building
- 2023: call for tenders for modular surfaces
- 2024/2025: completion
-
Shed for agricultural vehicles
- In agricultural zones
- 2023: planning
- 2023/24: completion
- Estimated investment: 1.69 million
-
Experimental greenhouse
- In agricultural zones
- Experimental greenhouse of max 5000 m2 for trials
- Estimated investment: 2 million