B1 - Micarna production ➤
B1 - Micarna production
Mobility platform ➤
B1 - Micarna production
Existing buildings ➤
B1 - Micarna production
B2 - Productions ➤
B1 - Micarna production
STEP AgriCo ➤
B1 - Micarna production ➤
A1 ➤
B1 - Micarn production
◀ A2
B1 - Micarn production
◀ A3
B1 - Micarn production
B1 - Micarna production
Description
- Production Micarna
Status
- In progress
- Planning 2022/23
- Realization 2024/25
Project sponsor
- Micarna
Further information
- Surface m2 of building sectors
92,975 - Estimated investments
460 000 000
Building 1712
Description
- Reception, offices, conference rooms, co-working facilities
- shared offices and laboratories for start-ups following the Agri & Co Challenge competition
Status
- Realized
Project sponsor
- ECPF
Further information
- Surface m2 of construction sectors
- Investments
300,000
Building 1715
Description
- Experimental greenhouse
- Re-use of the kennel as an experimental greenhouse for trials on a surface area of 100 to 600m2
Status
- Realized
- Commissioning 2022
Project sponsor
- ECPF
Further information
- Surface m2 of construction sectors
- Investments
800,000
Building 1701
Description
- Reception, offices, conference rooms, co-working facilities
- Renovation of the protected reception building
Status
- Realized
Project sponsor
- ECPF
Further information
- Surface m2 of construction sectors
- Investments
4,000,000
Building 1710
Description
- Laboratories, offices, small-scale production
- Laboratories and offices for SQTS and Start-ups
Status
- In progress
- Planning 2022
- Realization 2022/23
Project sponsor
- ECPF
Further information
- Surface m2 of construction sectors
- Estimated investments
17,800,000 (1710 + 1720)
Building 1720
Description
- Restaurant for the site
- 160-seat restaurant for site employees, operator currently being sought
Status
- In progress
- Planning 2022
- Realization 2022/23
Project sponsor
- ECPF
Further information
- Surface m2 of construction sectors
- Estimated investments
17,800,000 (1710 + 1720)
Building 1741/42
Description
- Workshop & production
- Conversion of protected storage and fire department buildings into workshops Work carried out in coordination with the new tower planned for the site
Status
- Standby
- Production as required
Project sponsor
- ECPF
Further information
- Surface m2 of construction sectors
- Estimated investments
3,700,000
Building 1740
Description
- Reconstruction of an existing building
Status
- In progress
- Planning 2022/23
- Realization 2024/25
Project sponsor
- Investor
Further information
- Surface m2 of construction sectors
- Estimated investments
Agricultural land
Description
- Shed for agricultural vehicles
- New agricultural hall on 100 ha of farmland
Status
- In progress
- Planning - 2022
- Pre-application 2021
- Permit application scheduled for April 2022
- Realization 2023
Project sponsor
- ECPF
Further information
- Surface m2 of construction sectors
- Estimated investments
1,800,000
Agricultural land
Description
- Experimental greenhouse
- Experimental greenhouse of max. 5,000m2 on agricultural land for trials on an area of approx. 800 to 1,000m2
Status
- Standby
- Production as required
Project sponsor
- ECPF
Further information
- Surface m2 of construction sectors
- Estimated investments
2,000,000
A1
Description
- Service buildings
- Sales outlet for products manufactured on site, crèche, exhibition areas, accommodation, hairdressers, fitness center, etc.
Status
- In progress
- Planning 2022
- Realization 2024
Project sponsor
- ECPF
Further information
- Surface m2 of construction areas
4,420 - Estimated investments
3,400,000
A2
Description
- Offices, laboratories, small-scale production
- new buildings under PDD by companies according to their needs (approx. 10,000m2 SP)
Status
- Staged production as required
Project sponsor
- Companies
Further information
- Surface m2 of building sectors
5,833 - Estimated investments
28,000,000
A3
Description
- Offices, laboratories, small-scale production
- New construction under PDD by companies according to their needs (approx. 18,000m2 SP)
Status
- Staged production as required
Project sponsor
- Companies
Further information
- Surface m2 of building sectors
10,818 - Estimated investments
50 000 000
Mobility platform
Description
- Mobility platform
- Construction in 2 stages, depending on requirements for main site access, MD and TIM traffic flows, public transport stops and silo parking.
Status
- In progress
- planning 2022/23
- MEP result in October 2022
- Planning 2023
- Realization 2024/25
Project sponsor
- ECPF (planning)
- Investor
Further information
- Surface m2 of construction areas
8,000 - Estimated investments
31 000 000
B2 - Production
Description
- Productions
- New buildings under PDD by companies according to their needs (approx. 40,000m2 SP)
Status
- Staged production as required
Project sponsor
- Companies
Further information
- Surface m2 of building sectors
36,842 - Estimated investments
100 000 000
AgriCo WWTP
Industrial Step
Description
- Pre-treatment and final treatment of industrial wastewater
Status
- In progress
- Planning 2022/ 2023
- Pre-project planning by ECPF
- Construction of the industrial WWTP by ECPF
- Realization 2024/2025
- Built by the ECPF and taken over by the municipal association once the regional WWTP has been built.
Project sponsor
- ECPF (planning)
Regional Step
Description
- Final treatment of household wastewater from the region
Status
- Realization from 2028
- planning and realization of the regional WWTP planned as a second stage by the municipal association
Project sponsor
- Local association
Further information
- Surface m2 of building sectors
11,406 - Estimated investments (industrial WWTP)
20,000,000